Aug 29, 2025
General News
The Road Program is scheduled to begin on August 28 and will continue through September 12 with milling and paving work.
Milling Schedule
- Thursday, August 28 – East Butler (start Shady Retreat)
- Friday, August 29 – Shady Retreat & Countrybrook Drive
- Tuesday, September 2 – Mahogany Court & North Shady Retreat
- Wednesday, September 3 – Pine Valley (Mill & Fill)
- Thursday, September 4 – Pine Valley (Mill & Fill)
- Friday, September 5 – Pinevale (Mill & Fill)
Paving Schedule
- Monday, September 8 – East Butler
- Tuesday, September 9 – Shady Retreat
- Wednesday, September 10 – Shady Retreat & Countrybrook Drive
- Thursday, September 11 – Mahogany Court & North Shady Retreat
- Friday, September 12 – North Shady Retreat