DTMA Updates

3/8/2021

Water main construction is complete except Springdale Road, which will follow sewer work

12/18

Week of 1/10- DTMA will be installing water main in Old New Road between Westaway Lane and Lower State Road.

Week of 1/3- DTMA will be installing water main in Old New Road between Davids Way and Bristol Road. Once complete, the contractor will install water main in Davids Way.

Week of 11/25- DTMA will be installing water main and water services in Old New Road between Westaway Lane and Davids Way.

Week of 11/16- DTMA completed the water main and service installation on Westaway Lane and Willow Lane.

All schedules weather dependent and subject to change

11/10

DTMA’s contractor will be back in the neighborhood installing water main on Willow Lane tomorrow subject to weather conditions.

11/6

DTMA’s contractor continues with water main installation along Westaway Lane and Willow Lane.

10/13

Water main installation began today, 10/13, on Stony Lane Circle. See photos below!

10/8

The Doylestown Township Municipal Authority will begin the installation of public water the week of October 12th, 2020.  The construction will begin on Stony Lane Circle.  Please check back for schedule updates.