Section Photos

Information

Pebble Ridge / Woodridge and Vicinity Sewer Project

Find information regarding the Pebble Ridge/ Woodridge and Vicinity Sewer Project.

NOTE: The Pebble Ridge Sewer Project is ongoing, and updates will be posted when needed. Please check back for more information.

Construction Drawings for Pebble Ridge/Woodridge Area Sanitary Sewers Updates from BCWSA

November 2, 2018 “Excavation has begun and we have installed 300 lf of 8” SDR-26 (pipe thickness) and Manholes CV#1 and CV#2.  We have begun to encounter rock which were are ripping out with our machine.

The week of the 5 of November we expect to continue installing pipe as well as manholes CV#3 and CV#4. This run will be a slow moving one as the cut in depth of this line will be approximately 22 feet below street level.  As always the schedule is  weather dependent.”

October 12, 2018 “BCWSA will continue saw cutting on Militia hill rd. the week of 10-15. Due to weather we have not been able to excavate at the interceptor, therefore we will be starting excavation at the easement next to Militia Hill rd. by the week of 10-22 possible sooner if weather permits.”

September 14, 2018 “ Material delivery for the first section (Almshouse and Militia hill roads) has been completed. Pipe installation has been delayed due to creek levels and rain expected next week. We expect to begin installation the week of 9-24-18”


August 24, 2018  Click Here to view the newest press release from BCWSA.


July 27, 2018 Letter from BCWSA.  Click Here to view the letter


*Beginning the week of July 23rd Gilmore and Associates will begin the stake out for the sewer project on those properties that provided easements.

*BCWSA are still on schedule to begin work on the sewer project the beginning of August. They will be starting with clearing along the creek side of the project before moving into the neighborhood.


Pebble Ridge/Woodridge & Vicinity Approved Agreement with BCWSA

October 30, 2017 Click Here to view Resolution No. 1980

Pebble Ridge/Woodridge & Vicinity Final Draft Agreement with BCWSA

Click Here to view the Pebble Ridge/Woodridge Area Sanitary Sewer Construction Agreement

PENNVEST Loan Information

6/6/2018 Township Completes Closing on the PENNVEST Loan.

Click Here to view the attached letter with a tentative schedule and timeline for construction.

Public Water Survey in Pebble Ridge/Woodridge

Click Here to view the Municipal Authority’s letter to residents whose purpose is to gauge the interest in having public water in the surrounding vicinity of the Pebble Ridge/Woodridge neighborhood.

Township Awards Bids and Approves Paperwork for PENNVEST Loan

On April 17, 2018 the Doylestown Township Board of Supervisors approved the bids for the pump station and the clearing and grubbing for the project. Click here for the article. Be advised that BCWSA still has to approve the bids.

Also, the Board approved the required paperwork associated with the PENNVEST loan. We anticipate closing on the loan in late May. We’ll post additional updates as information becomes available.

Low Interest Loan Application Approved

At their meeting on January 31, 2018 the PennVest Board approved the Township’s application for the low interest loan to pay for the costs associated with the construction and installation of the Pebble Ridge/Woodridge Sewer Project. The receipt of funds from PennVest is subject to a formal settlement, which the Township anticipates will occur within the next four to six months.  As indicated during meetings this past summer, the low interest loan interest rates and loan term offered to us by PennVest will be passed along and will be available to residents as part of a loan program offered through BCWSA to pay for each resident’s costs of the public portion of the Project.

In addition, BCWSA’s engineer Gilmore & Associates will be putting out bids for construction of the pump station, as well as clearing for the project. Permits for the project from PennDot, PA DEP and the Bucks County Conservation District are being finalized.

We still anticipate this project getting underway during the summer of 2018.

Ordinances

Click Here to view Ordinance No. 384

Below is the proposed and revised ordinance for consideration on 8/15/17. The Board of Supervisors adopted this ordinance at their meeting on 8/15/17.

Proposed Revised Sewer Ordinance

Below are the responses to questions from residents along with a process flow chart:

Responses to Residents Questions PRWR Sewer Project

Related Past Documents and Materials:

Proposed Ordinance

Easements: On March 3rd, 2015 the Doylestown Township Board of Supervisors authorized the acquisition of the necessary easements for this project.  Once the easements are received, Bucks County Water and Sewer Authority will move forward with the bidding process.

Presentations & Other Information

Don’t have Adobe Reader? Download it here.